Implementation Plan
Overview
This implementation plan outlines the strategic approach for developing "The Link" EV Charging Network across Illinois, with a focus on rural and underserved communities. The plan details a phased deployment strategy, site selection criteria, technology implementation approach, and risk mitigation strategies to ensure successful project execution.
Phased Deployment Strategy
Phase 1: Planning & Design (Months 1-3)
Site Selection and Acquisition
- Conduct comprehensive GIS analysis to identify optimal locations
- Perform site assessments for technical feasibility
- Initiate discussions with property owners and local governments
- Secure initial site agreements for first 5 hub locations
Permitting and Regulatory Compliance
- Engage with local building departments to understand requirements
- Submit permit applications for initial hub locations
- Coordinate with utilities for grid connection approvals
- Ensure compliance with ADA and other accessibility standards
Community Engagement and Partnership Development
- Host community forums in target deployment areas
- Establish relationships with local businesses and organizations
- Develop partnership agreements with key stakeholders
- Create community advisory boards for ongoing input
Detailed Engineering and Architectural Design
- Finalize hub architectural designs with community input
- Complete electrical engineering plans for charging infrastructure
- Develop solar integration and battery storage specifications
- Create detailed construction documents for bidding
Phase 2: Initial Deployment (Months 4-9)
Construction of First 3-5 Link Hubs
- Select construction contractors through competitive bidding
- Begin site preparation and foundation work
- Install electrical infrastructure and grid connections
- Construct hub buildings and install charging equipment
- Deploy solar arrays and battery storage systems
- Complete landscaping and site finishing
Development and Testing of Management Software
- Finalize development of charging management system
- Integrate payment processing and user authentication
- Develop mobile application for user interface
- Conduct extensive testing with focus groups
- Implement feedback and refine user experience
Training of Initial Staff and Service Providers
- Hire and train hub managers and technical staff
- Develop standard operating procedures
- Conduct safety and emergency response training
- Establish maintenance protocols and schedules
Launch of Pilot Subscription Services
- Initiate marketing campaign in pilot communities
- Begin accepting subscription applications
- Deploy initial fleet of electric vehicles
- Implement customer onboarding and training
- Collect and analyze initial usage data
Phase 3: Expansion (Months 10-15)
Construction of Additional Link Hubs
- Begin construction on next wave of hub locations
- Apply lessons learned from initial deployments
- Streamline construction processes for efficiency
- Implement design improvements based on user feedback
Refinement of Operational Procedures
- Analyze data from initial operations to identify improvements
- Optimize staffing models and service hours
- Enhance maintenance procedures based on experience
- Improve energy management and charging strategies
Expansion of Subscription Services and Fleet
- Increase vehicle fleet based on demand analysis
- Expand subscription offerings with refined pricing models
- Develop corporate and institutional subscription packages
- Implement loyalty and referral programs
Implementation of Community Programs and Partnerships
- Launch Community Access Program for low-income users
- Develop educational initiatives with local schools
- Establish workforce development programs
- Create community events and engagement opportunities
Site Selection Criteria
Transportation Factors
- Proximity to major transportation corridors and highways
- Intersection with existing public transit routes
- Traffic patterns and volume in surrounding area
- Accessibility from multiple directions
- Visibility to passing traffic
Community Needs Assessment
- Current EV adoption rates in the community
- Existing charging infrastructure availability
- Distance to nearest alternative charging options
- Community demographics and transportation needs
- Potential impact on local economic development
Technical Feasibility
- Availability of adequate electrical service
- Potential for solar generation (sun exposure, shading)
- Site size and configuration requirements
- Soil conditions and drainage considerations
- Existing infrastructure that can be leveraged
Equity Considerations
- Distribution across diverse communities
- Focus on historically underserved areas
- Accessibility for low-income residents
- Proximity to multi-family housing
- Connection to essential services (healthcare, education, employment)
Partnership Opportunities
- Potential for co-location with local businesses
- Interest from municipal or county governments
- Proximity to educational institutions
- Alignment with existing community development plans
- Potential for shared investment or resources
Technology Implementation Approach
Charging Technology Deployment
- Install multiple DC Fast Charging ports (150kW) at each hub
- Include Level 2 charging options for longer dwell times
- Ensure compatibility with all major connector types (CCS, CHAdeMO, Tesla)
- Implement modular design to allow for future technology upgrades
- Phase deployment to incorporate emerging technologies as they mature
Renewable Energy Integration
- Deploy solar photovoltaic arrays sized appropriately for each location
- Install battery storage systems to optimize renewable energy usage
- Implement smart energy management systems for grid interaction
- Monitor and analyze energy production and consumption patterns
- Develop strategies for increasing renewable percentage over time
Software and Digital Systems
- Deploy cloud-based charging management platform
- Implement secure payment processing systems
- Develop user-friendly mobile application interface
- Create data analytics dashboard for performance monitoring
- Establish API connections with partner systems and services
Fleet Management Systems
- Implement vehicle telematics and tracking
- Deploy reservation and scheduling software
- Create maintenance tracking and alert systems
- Develop driver authentication and access controls
- Establish charging optimization algorithms
Security and Safety Systems
- Install comprehensive video surveillance
- Implement lighting designed for safety and security
- Deploy emergency call systems at all locations
- Create cybersecurity protocols for all digital systems
- Develop incident response procedures
Risk Mitigation Strategies
Financial Risks
Risk: Funding delays or shortfalls
- Mitigation: Secure diverse funding sources, including private investment, grants, and revenue-based financing
- Contingency: Phased implementation plan that can be adjusted based on available funding
Risk: Higher than anticipated construction or equipment costs
- Mitigation: Detailed cost estimation with appropriate contingencies
- Contingency: Value engineering options identified in advance
Technical Risks
Risk: Grid capacity limitations
- Mitigation: Thorough utility coordination during planning phase
- Contingency: Battery storage systems to reduce peak demand
Risk: Technology obsolescence
- Mitigation: Modular design approach allowing for component upgrades
- Contingency: Technology roadmap with planned refresh cycles
Operational Risks
Risk: Lower than projected utilization
- Mitigation: Comprehensive marketing strategy and community engagement
- Contingency: Flexible pricing models and promotion strategies
Risk: Maintenance and reliability issues
- Mitigation: Preventative maintenance program and remote monitoring
- Contingency: Service level agreements with equipment providers
Regulatory Risks
Risk: Permitting delays
- Mitigation: Early engagement with regulatory authorities
- Contingency: Parallel processing of multiple sites to maintain overall timeline
Risk: Policy changes affecting EV incentives
- Mitigation: Diversified business model not solely dependent on incentives
- Contingency: Adaptable pricing structure that can respond to policy changes
Community Acceptance Risks
Risk: Community opposition to specific locations
- Mitigation: Early and transparent community engagement process
- Contingency: Alternative site options identified for each planned location
Risk: Concerns about equity and accessibility
- Mitigation: Inclusive planning process with diverse stakeholder input
- Contingency: Community benefits agreements with specific commitments
Implementation Timeline
Month | Key Activities | Milestones |
---|---|---|
1-2 | Site selection analysis, community engagement initiation | Preliminary site list finalized |
3 | Permitting applications, detailed design completion | Design documents completed |
4-5 | Construction begins on first hub, software development | Groundbreaking ceremony |
6-7 | Equipment installation, staff hiring and training | First hub structure completed |
8 | System testing, user experience refinement | Software platform launch |
9 | First hub operational, subscription service launch | Grand opening event |
10-11 | Data collection and analysis, construction of additional hubs | Operational data report |
12-13 | Expansion of subscription services, refinement of operations | Fleet expansion |
14-15 | Community program implementation, preparation for next phase | Phase completion report |
Resource Requirements
Human Resources
- Project Management Team (3 FTE)
- Engineering and Technical Staff (5 FTE)
- Construction Management (2 FTE)
- Operations and Maintenance Team (8 FTE)
- Customer Service and Community Engagement (4 FTE)
- Administrative Support (3 FTE)
Equipment and Materials
- Charging Equipment (DC Fast Chargers, Level 2 Chargers)
- Solar PV Systems and Battery Storage
- Construction Materials for Hub Structures
- Fleet Vehicles for Subscription Services
- IT Infrastructure and Software Systems
External Services
- Architectural and Engineering Services
- Construction Contractors
- Electrical Contractors
- Software Development Services
- Legal and Regulatory Compliance Services
Monitoring and Evaluation
Throughout implementation, Unity Fleet will maintain a robust monitoring and evaluation system to track progress, identify issues, and ensure the project remains on schedule and within budget. Key components include:
- Weekly project team meetings to review progress and address challenges
- Monthly progress reports to stakeholders and funding partners
- Quarterly comprehensive reviews of project metrics and milestones
- Continuous data collection on construction progress, expenditures, and early operational metrics
- Regular community feedback sessions to ensure the project meets local needs
Conclusion
This implementation plan provides a comprehensive roadmap for the successful development of "The Link" EV Charging Network. The phased approach allows for careful planning, community input, and the incorporation of lessons learned throughout the process. By addressing potential risks proactively and establishing clear criteria for decision-making, Unity Fleet will ensure that the project delivers maximum benefit to Illinois communities while maintaining financial and operational sustainability.
Unity Fleet is committed to transparent, inclusive implementation that prioritizes community needs and creates lasting positive impact. We look forward to working with IDOT and other partners to bring this transformative project to fruition.